19.02.2017 - 19.02.2017
Tajikistan
Overall project value (EUR) | 384615 Euro (500000 USD) |
No. of staff provided | N/A |
Name of Client | Ministry of Transport of Rep. of Tajikistan |
Financing agency | Asian Development Bank (ADB) |
Name of partners | ENGConsult Ltd. (Canada); N/A; N/A |
Detailed Narrative Description of Project | The objective of the TA was to prepare the Project which aimed to improve sections of the road running from Dushanbe northeast to the border with the Kyrgyz Republic that were not rehabilitated under the ongoing Dushanbe-Kyrgyz Border Road Rehabilitation Project, Phase I (Loan 2062-TAJ(SF)), as well as rural roads feeding into the Project road. |
Detailed Narrative Description of Services provided | N/A |